Category Archives: Case Study – Axbridge Farm

Would you like dust with that, Sir?

This is a short film taken at the Axbridge farm where we have installed four Eta Hack 200 biomass boilers that have been modified to burn miscanthus instead of wood chip. As you can see, the poultry houses have been … Continue reading

Posted in Case Study - Axbridge Farm | Tagged , , | Comments Off

Commercial Biomass for the complete package

Commercial Biomass Partnership spent a long weekend installing the pipework to these Drapervent units. All four sheds were plumbed in four days over this turnaround. We could have managed it in three days if the scissor lift platforms had worked … Continue reading

Posted in Case Study - Axbridge Farm | Tagged , , , | Comments Off

Progress on pods

Didn’t quite get them all finished by the end of the week, but we are three quarters of the way there. My biggest problem is my phone doesn’t stop ringing, but against the backdrop of the biggest recession since the … Continue reading

Posted in Case Study - Axbridge Farm | Comments Off

Axbridge Poultry Farm gets four Eta Biomass Boilers

The workshop took delivery of another four frames for our biomass pods. These should be finished and ready for delivery by the end of the week. Once they are cleared away the workshop will be taking delivery of another five … Continue reading

Posted in Case Study - Axbridge Farm | Comments Off

Four ETA Wood Chip Boilers on Axbridge Farm

We received the deposit from our client last week, and work begins today on site to extend his sheds to incorporate the boilerhouses and fuel stores. These four individual 199kw wood chip boilers will actually run on myscanthus, as the … Continue reading